Municipal

Broadway Storm Sewer and Wolf Creek Outfall Improvements

Project details

Project Type

Municipal

Client

City of Dayton

Contract Period

2021

Construction Manager

Architect

Engineer

City of Dayton - Department of Water – Division of Water Engineering

Contract Value

$615,000

Scope

Exterior Services

project DESCRIPTION

This project, performed for the City of Dayton, consists of lining approximately 766 linear feet of 48 to 54-inch storm sewer with a centrifugally cast concrete pipe (CCCP) liner on N. Broadway Street, replacing the Wolf Creek WCL-10 Outfall, installing 183 linear feet of new 48-inch storm sewer pipe, installing 50 linear feet of 12-inch storm pipe, revetment work, demolition work and restoration work.

view live construction progress here